試卷名稱 信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項(xiàng)目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A company obtained a project in a new region. The project manager identified the risk of the project and the sort. Which of the following actions should the project manager take next?
A、 Plan Risk Responses process.
B、 Develop appropriate measures, and improve the positive risk or opportunity.
C、 Improve opportunities and reduce threats.
D、 Update risk information.