aaa成人,欧美黑人xxxx猛性大交,致命弯道2在线观看免费完整版在线,亚洲情侣视频,91成人在线网站,色戒完整版免费观看无删减版,99综合网

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Two months into a designed project, the customer requested a modification to the project .The change was made without notify the project manager .During the final testing phase, result were different from what was planned for.his scenario is an example of which of following ?
A、Poor definition of the test plan
B、Poor development of quality management
C、Poor use of scope change control
D、Poor adherence to the communication plan


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容