試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(2)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(2)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內容

The project manager for a construction project acquires the approval on a change order to provide additional concrete foundations. This change is analyzed using a Monte Carlo simulation but weather conditions are overlooked. Also, the risk of physical harm to the team members performing the outdoor work was not considered, The project must be finished on time, as part of the foundation for venue of a local festival.What should the project manager do next?
A、Accept that the project goes into default, and pay the price for not finishing scope on time as stipulated in the contract
B、Stick to the original plan and reversal procedure
C、Consult the project sponsor and meet with the major stakeholders to look for alternatives
D、Keep this new knowledge within the project team, and hope for a change in temperature that will allow completion of the project